Building Code Wizard

Detached ADU — 9526 Babauta Rd, San Diego CA 92129

9526 Babauta Rd, San Diego CA 92129

Detached ADUActiveRS-1-11
APN
3155610400
Subtype
Rear yard
Proposed SF
800 sf
Permit Count
0 permits
Scope of Work
New construction
Last Updated
Updated Jan 1

What Solar / PV requires

Permits & approvals required

No permit unique to this section — covered by the project's building permit (see Permits → Permit Requirements).

Review disciplines

  • Public Utilities (water/sewer) reviewVerify
    Required when a NEW or upsized water/sewer connection is proposed. A shared connection to the primary dwelling may not need separate review — verify the connection type.
    Project involves water/sewer plumbing.
    From the code
    • upon a combination of the number of Equivalent Dwelling Units (EDU) being reviewed and whether or not a change is being made to a meter. The plan check fee is based per EDU and is charged for both irrigation and domestic meters. For the purposes ... assessing these fees, 20 fixture units are given a value of one EDU. Table 501D lists Water and Sewer plan check fees. Water & Sewer Capacity Fees Water and Sewer Capacity Fees are collected on behalf of the Public Utilities Department and are determined during SD Information Bulletin 501, p. 1
    • Water services and sewer lateral installation fees associated with new construction are collected on behalf of the Public Utilities Department and are determined during the building permit plan review process. See “Schedule for Water and Sewer Fees” for water and sewer services, including potable ... reclaimed water for the City of San Diego. A Water Meter Data Card (DS-16) is used to determine the correct size required for the water meter, service and sewer lateral. Storm Water High Priority & Areas of Special Biological Significance (ASBS) Inspection Fee The Regional SD Information Bulletin 501, p. 1

Submittal requirements

No submittal specific to this section for this project.

Reference documents

Applicable documents — Utilities / Solar / PV · 3 · click to expand

RankTopics CoveredSection Citation
1
California Code of Regulations Title 24, Part 6 — Building Energy Efficiency Standards
Title 24 energy, Solar / PV readiness
Title 24 Part 6 — Energy Code 2022
2
City of San Diego Information Bulletin 301 — Permit for Installation of Solar Photovoltaic (PV)
Permitting, Solar PV
SD Information Bulletin 301
3
BIA-SD ADU Design Checklist v3advisoryCandidate (RAG)
Building Industry Association of San Diego — ADU Design Checklist v3
Topics pending review
BIA-SD ADU Design Checklist v3

Reference tables (2)

Solar PV Permit Fees — Single System/Inverter

Table Capture v1.1
ItemFee
First System/Inverter Plan Check$154.20
First System/Inverter Inspection$275.80

Solar PV Permit Fees — Per 100 kW (Larger Systems)

Table Capture v1.1
ItemFee
First 100 kW Plan Check$758.00
Each Additional 100 kW Plan Check$264.00
First 100 kW Inspection$290.00
Each Additional 100 kW Inspection$145.00

An additional electrical permit fee will be assessed for the new electrical infrastructure proposed for the project; see IB 301 for additional electrical permit fee.