City of San Diego Information Bulletin 100 — Estimated Due Dates for Building Permits
Development Services Site Menu DSD Home Permits, Approvals & Inspections News & Programs Zoning Codes & Regulations Forms & Publications Public Hearings, Meetings & Notices Fees Records Building & Land Use Enforcement Estimated Due Dates for Building Permits INFORMATION BULLETIN 100 May 2026 View All Information Bulletins IN THIS BULLETIN: Building Permit Applications Single Dwelling Units/Duplex and Townhome Estimated Due Dates All Other Building Permits Estimated Due Dates This Information Bulletin describes the estimated due dates for Building Permit applications submitted to the Development Services Department (DSD). These are estimates and are not guaranteed, as DSD cannot limit the number of submitted projects, so the workload is variable. For example, DSD often receives more Building Permit applications in the month before a new building code is adopted. Still, DSD works to meet the estimated due dates as much as possible. View the average review times for a variety of review disciplines.
Projects that qualify for Rapid Review are not included in the tables below; projects in Rapid Review receive due dates of 6 business days for the first review and 2 business days for rechecks. I. Building Permit Applications When a building permit application is submitted, the size of the project is determined based on the tables listed below. If the project includes multiple buildings, the next category will be used. If more than 50% of the existing building square footage is removed and reconstructed, the building will be considered a new building for the purposes of due dates.
SINGLE DWELLING UNITS/DUPLEX/TOWNHOME Short Medium Long Accessory structure additions (e.g., decks, stairs, fences, fireplaces, equipment anchorage on grade, equipment enclosure) Alterations/additions 3,000 sf with no increase in density Foundation repair except piles/caissons Retaining walls 10 ft Swimming pool Any project with a prior discretionary permit Alteration/addition 3,000-7,000 sf Foundation repair using piles/caissons Retaining walls greater than 10 ft Shoring walls New up to 7,000 sf Alterations or addition 7,000 sf New 7,000 sf ALL OTHER BUILDING PERMITS Short Medium Long Complex Accessory structure additions Alteration/Addition to an individual dwelling unit Change of occupancy other than to A or H occupancy type Commercial coaches Foundation repair except piles/caissons Paint spray booth Parking lots only Retaining wall 10 ft Signs Storefront alteration TIs/ Alterations up to 10,000 sf (except for restaurants/ bars/clubs or with hazmat) Projects with a prior discretionary permit Additions Antennas Change of occupancy to A or H Church 10,000 sf Foundation repair using piles/caissons MDU 20 units Non-residential building 2 stories 20,000 sf Parking structure 3 stories Restaurant/bar/club up to 10,000 sf Retaining wall 10 ft School 10,000 sf Seismic retrofit 4 stories Storage racks Shoring walls Swimming pools TIs/Alterations 10,000 sf for restaurants/bars or with hazmat TIs 10,000-50,000 sf Church 10,000 sf Hotel/motel 5 stories Non-residential TIs 50,000 sf Non-residential building more than 2 stories but less than 5 stories Restaurants/bars/club 10,000 sf School 10,000 sf Seismic retrofit 4 stories Multiple Dwelling Units with 20-100 units New buildings 7 or more stories above grade level Parking structure 5 stories and 100,000 sf Hotel/motel (new) 5 stories Multiple Dwelling Units 100 units Multi-plex theaters/auditoriums Non-residential building 5 stories or more Parking structure 5 stories and 100,000 sf Shopping malls Mixed-use buildings 3 stories II.
Single Dwelling Units/Duplex and Townhome Estimated Due Dates Listed below are the estimated due dates (in business days) for projects that are single dwelling units (homes), duplexes and townhomes. Apartments and condominium buildings that contain more than 2 dwelling units are covered in the All Other Building Permits category. Short Medium Long Final Version First Review Recheck First Review Recheck First Review Recheck 5 8 6 10 6 15 6 III. All Other Building Permits Estimated Due Dates Listed below are the estimated due dates (in business days) for all building projects that are not single-family units (homes), duplexes and townhomes. This includes apartments, condominiums, offices, retail, restaurants, etc. For information on the Expedite and Express programs, see Information Bulletin 538 and Information Bulletin 700 , respectively. *Note that Complex timelines only occur for the Structural 1 and Structural 2 review disciplines. All other due dates for complex projects follow the Long due dates. I.
Standard Reviews Short Medium Long Complex* Final Version First Review Recheck First Review Recheck First Review Recheck First Review Recheck 5 10 6 20 10 40 20 60 30 II. Expedite Reviews Short Medium Long Complex* Final Version First Review Recheck First Review Recheck First Review Recheck First Review Recheck 5 8 6 15 8 30 15 60 30 III. Express Reviews Short Medium Long Complex* Final Version First Review Recheck First Review Recheck First Review Recheck First Review Recheck 5 6 6 10 6 20 10 30 15
Ingested verbatim from the official source for in-app search; confirm against “View official source” for legal use.
| Short | Medium | Long |
|---|---|---|
| Section | ||
| Accessory structure additions (e.g., decks, stairs, fences, fireplaces, equipment anchorage on grade, equipment enclosure) | Any project with a prior discretionary permit | Alterations or addition >7,000 sf |
| Alterations/additions < 3,000 sf with no increase in density | Alteration/addition 3,000-7,000 sf | New > 7,000 sf |
| Foundation repair except piles/caissons | Foundation repair using piles/caissons | |
| Retaining walls < 10 ft | Retaining walls greater than 10 ft | |
| Swimming pool | Shoring walls | |
| New up to 7,000 sf | ||
| Short | Medium | Long | Complex |
|---|---|---|---|
| Accessory structure additions | Projects with a prior discretionary permit | Church >10,000 sf | Hotel/motel (new) > 5 stories |
| Alteration/Addition to an individual dwelling unit | Additions | Hotel/motel < 5 stories | Multiple Dwelling Units >100 units |
| Change of occupancy other than to A or H occupancy type | Antennas | Non-residential TIs > 50,000 sf | Multi-plex theaters/auditoriums |
| Commercial coaches | Change of occupancy to A or H | Non-residential building more than 2 stories but less than 5 stories | Non-residential building 5 stories or more |
| Foundation repair except piles/caissons | Church <10,000 sf | Restaurants/bars/club > 10,000 sf | Parking structure > 5 stories and 100,000 sf |
| Paint spray booth | Foundation repair using piles/caissons | School >10,000 sf | Shopping malls |
| Parking lots only | MDU < 20 units | Seismic retrofit > 4 stories | Mixed-use buildings > 3 stories |
| Retaining wall < 10 ft | Non-residential building < 2 stories < 20,000 sf | Multiple Dwelling Units with 20-100 units | |
| Signs | Parking structure < 3 stories | New buildings 7 or more stories above grade level | |
| Storefront alteration | Restaurant/bar/club up to 10,000 sf | Parking structure <5 stories and 100,000 sf | |
| TIs/ Alterations up to 10,000 sf (except for restaurants/bars/clubs or with hazmat) | Retaining wall >10 ft | ||
| School < 10,000 sf | |||
| Seismic retrofit < 4 stories | |||
| Storage racks | |||
| Shoring walls | |||
| Swimming pools | |||
| TIs/Alterations < 10,000 sf for restaurants/bars or with hazmat | |||
| TIs 10,000-50,000 sf |
| Short | Medium | Long | Final Version | |||
|---|---|---|---|---|---|---|
| First Review | Recheck | First Review | Recheck | First Review | Recheck | 5 |
| 8 | 6 | 10 | 6 | 15 | 6 |
| Short First Review | Recheck | Medium First Review | Recheck | Long First Review | Recheck | Complex* First Review | Recheck | Final Version |
|---|---|---|---|---|---|---|---|---|
| 10 | 6 | 20 | 10 | 40 | 20 | 60 | 30 | 5 |
| Short First Review | Short Recheck | Medium First Review | Medium Recheck | Long First Review | Long Recheck | Complex* First Review | Complex* Recheck | Final Version |
|---|---|---|---|---|---|---|---|---|
| 8 | 6 | 15 | 8 | 30 | 15 | 60 | 30 | 5 |
| Short | Short | Medium | Medium | Long | Long | Complex* | Complex* | Final Version |
|---|---|---|---|---|---|---|---|---|
| First Review | Recheck | First Review | Recheck | First Review | Recheck | First Review | Recheck | 5 |
| 6 | 6 | 10 | 6 | 20 | 10 | 30 | 15 |